Technical Feasibility

Engineering specifications, construction timeline, and regulatory pathway for the Colossus Utilidor.

Engineering Specifications

ParameterValue
Tunnel
Tunnel Length5,280 ft (1 mile)
Inner Diameter12 ft (Prufrock standard)
Depth Below Grade30–50 ft
Boring MethodPrufrock TBM (The Boring Company)
LiningPrecast concrete segments (15" thick)
Power Distribution (150 MW)
Total Capacity150 MW
13.8kV Feeders4x at 35 MW each = 140 MW
480V Buses2x at 5 MW each = 10 MW
Annual Transfer1,314,000 MWh/year
Annual Savings$19.7M (3% loss reduction)
Fiber Optic (20,736 Strands)
Total Strands20,736 strands
Trunk Cables6x 3,456-strand OS2 single-mode
Primary DCI4 trunks (13,824 strands)
Redundant DCI2 trunks (6,912 strands)
Bandwidth16.6 Pb/s theoretical
800G Links10,368 simultaneous
Chilled Water (12,000 GPM)
Total Flow12,000 GPM
Main Supply24" pipe — 10,000 GPM
Redundant Supply12" pipe — 2,000 GPM
Main Return18" pipe — 10,000 GPM
Redundant Return12" pipe — 2,000 GPM
Thermal Capacity85 MW (12°F ΔT)
Vehicle Transport (90 Trips/Day)
Vehicles/Hour6 vehicles/hr
Transit Time8 minutes
Daily Capacity90 trips/day (15-hr window)
Payload2,000 lbs (8–12 GPU servers)
Personnel12–18/hour
SecurityNone required (enclosed tunnel)
Infrastructure
Service Walkway3 ft wide, continuous
VentilationForced air, longitudinal
Fire SuppressionWet standpipe system
State Line Crossing~35.0042°N latitude
Geology at DepthAlluvial clay (favorable for EPB TBM)
* * *

Construction Timeline

Total estimated timeline: ~22 months. Click each phase for details.

* * *

Regulatory Pathway